- Approval of 18.32 hector government land for resettlement by cabinet decision
- Geological test of site by technical team of National Reconstruction Authority (NRA)
- Approval by the technical team
- Development of Master Plan and design of individual identical houses
- Approval of Master Plan by NRA
- Construction of 573 houses with sanitation facilities
- Total cost 481,732,467.95 rupees